The enforcement record of 29 CFR 1910.119
The Case Record

Major OSHA Process Safety Management enforcement actions

Landmark PSM cases with the penalties OSHA proposed, what inspectors found, and how they ended. Every entry links to its source. For citations issued in the last 12 months, see the live tracker.

YearFacilityWhat OSHA foundTypeProposed
2009BP Products North America
Texas City, TX · Refinery
270 failure-to-abate notices from the 2005 settlement ($56.7M) plus 439 new willful PSM violations, largely pressure relief ($30.7M).
Outcome: BP paid $50.6M (2010) to settle the failure-to-abate items and $13.03M (2012) to resolve 409 willful citations.
Source: OH&S · MPR/AP · ENR
WillfulFTA$87,430,000
2005BP Products North America
Texas City, TX · Refinery
Citations following the March 2005 isomerization unit explosion that killed 15 workers and injured 170.
Outcome: Then the largest OSHA penalty on record; settlement terms later became the basis for the 2009 failure-to-abate citations.
Source: OGJ
Willful$21,000,000
2010BP-Husky Refining
Oregon (Toledo), OH · Refinery
42 willful (39 per-instance) and 20 serious violations: inadequate pressure relief for process units, fuel accumulation in process heaters, building collapse risk from fire.
Source: U.S. DOL
WillfulSerious$3,042,000
2013Chevron USA (Cal/OSHA)
Richmond, CA · Refinery
25 citations (11 willful serious) after the Aug 2012 crude unit fire: corroded pipe left in service despite internal recommendations dating to 2002.
Outcome: The maximum allowed under California law at the time. Settled 2017: Cal/OSHA withdrew or downgraded a number of the violations; Chevron committed to replace carbon steel piping in corrosive service (est. $15M), add training, and pay an additional $227,300.
Source: OH&S · Hydrocarbon Processing
WillfulSerious$963,200
2010WRR Environmental Services
Eau Claire, WI · Chemical processing
14 willful and 1 serious violation following a June 2010 explosion and fire.
Source: U.S. DOL
WillfulSerious$787,000
2020TPC Group
Port Neches, TX · Chemical
Cited after the November 2019 butadiene unit explosions and fires, including 3 willful violations for failing to develop and implement emergency shutdown procedures and to inspect and test process vessels and piping.
Source: U.S. DOL
Willful$514,692
2021Limetree Bay Refining
St. Croix, USVI · Refinery
20 PSM violations after oil and vapor releases and flaring events in February and May 2021.
Source: U.S. DOL
Serious$259,407
2009Sunoco
Marcus Hook, PA · Refinery
Refinery NEP inspection: 5 repeat violations ($125,000) for inaccurate piping diagrams, inadequate operating procedures and outdated process safety information, plus 20 serious ($77,000) including an inadequate PHA and inaccurate inspection records.
Source: OH&S
RepeatSerious$202,000
2024AJLS Enterprises (Schoep's Ice Cream)
Madison, WI · Ammonia refrigeration
12 serious violations after workers were exposed to anhydrous ammonia, including PSM failures: equipment not documented as RAGAGEP-consistent, audit findings not addressed, changes not managed.
Source: U.S. DOL
Serious$145,097
2020Philadelphia Energy Solutions
Philadelphia, PA · Refinery
Serious PSM violations after the June 2019 fire and explosions involving hydrofluoric acid and flammable hydrocarbons.
Source: U.S. DOL
Serious$132,600
2022Pilgrim's Pride
Canton, GA · Ammonia refrigeration
9 serious violations for inadequately implementing and maintaining the PSM program for anhydrous ammonia refrigeration.
Source: U.S. DOL
Serious$110,630
2015Seaboard Foods
Guymon, OK · Ammonia refrigeration
7 serious PSM violations in an ammonia refrigeration system.
Source: U.S. DOL
Serious$51,000

All amounts are proposed penalties at the time of citation. Employers can contest before the Occupational Safety and Health Review Commission (or a state review board for state-plan cases), and final amounts often differ. FTA = failure to abate. Chevron Richmond was cited by Cal/OSHA under California's state plan.

Before the inspector does